Engineering, Design & Consulting projects

Country Client Commodity Project scope Project status
South Africa South 32 – Mamatwan Mine Top-Cut Material Processing Manganese

The Pre-Feasibility Study (PFS) aimed at identifying the most practical and effective processing solution for the top-cut material.

The PFS was required to investigate, select, and consolidate the preferred processing alternative to progress into Feasibility Study (FS), develop a Total Installed Cost (TIC) estimate and schedule, and establish an FS scope to minimise the risk of cost overruns and/or schedule delays during the execution of the Project

February 2024
South Africa Ivanplats – Platreef Shaft 2 Platinum

UMS are fulfilling the role of the owners’ team for the Platreef Shaft 2 construction project. This includes supporting and managing the following contractors:

  • Murray and Roberts
    • Raise bore drilling
    • Diamond drilling
    • Shaft sinking – slipe, line and equipping
  • Stefanutti Stocks
    • Headgear slide/construction
    • Headgear structural construction
In Progress
South Africa Sibanye – Burnstone Plant Refurbishment Project Gold

Refurbishment and recommissioning of the Burnstone Gold Plant, which included the following:

  • Service, repair, refurbish and/or replace chosen mechanical, electrical and control & instrumentation equipment/spares at the Plant
  • Service, repair, refurbish and/or replace chosen civil and structural related infrastructure at the Plant
  •  Service, repair, refurbish and/or replace chosen mechanical, electrical and control & instrumentation equipment/spares at the Tailings Storage Facility (TSF)
  • Service, repair, refurbish and/or replace chosen civil and structural related infrastructure at the Tailings Storage Facility (TSF)
  • Commission the Process Plant and related facilities such that it is ready for production
February 2024
South Africa Pilanesberg Platinum Mines – Sedibelo Development Project Platinum

The design scope for UMS included:

  • Site layout and infrastructure
  • Chairlift decline and travelling ways.
  • Conveyor decline and “training decline”
  • Main decline
  • Level and access decline including workshop, ventilation pass and level dams.
  • Decline support (anchors, wetcrete and tendons)
  • Cover drilling
  • Raise boring
  • Brow stabilisation
September 2023
South Africa Impala 1# Platinum Full shaft audit of aging shaft infrastructure with upgrade/optimisation recommendations. 2021
South Africa Evander/Pan Africa Gold Design of a compensating tower thereby enabling safe pillar extraction of remaining ore reserves in an aging mine. 2019-2020
Botswana Karowe diamond mine Diamonds

The Karowe Underground Project (KUP) scope of works entailed the design and engineering for the blind sinking of two vertical shafts. The main production shaft will have a finished internal diameter of 8.5m and be sunk to a depth of 765m below surface level. The ventilation shaft will have a finished diameter of 6m and be sunk to a depth of 755m.

In addition to the shaft sinking activities, the scope of works includes the design and engineering for the equipping of the production shaft for permanent configuration and initial lateral development.

Brazil Ero Copper – Caraíba Pilar Mine Copper

The UMS scope included the design and construction of the new vertical mine shaft and underground rock handling arrangements The ERO Brasil Caraiba project.

Design scope was for a shaft  approximately 1,500m deep with a hoisting capacity of 2.2 million tonnes per annum of ore and waste from underground to surface. The shaft will also be capable of raising and lowering approximately 840 persons per day, to and from underground.

The underground rock handling system included haul truck tips for ore and waste rock, storage silos for run-of-mine and crushed ore and waste rock, an underground primary crushing station, and conveyors to transfer the rock to the vertical shaft.

To be completed in 2026
South Africa Sibanye Stillwater Ikamva Kloof mine Design of level declines. 2022
South Africa Vanadium Resources Vanadium Pre-feasibility and definitive feasibility study. 2021- 2022
South Africa New Denmark – Seriti Coal Design of new conveyors, man cages and platforms. 2020-  2021
Zimbabwe Zimplats Platinum Implementation of a debottlenecking project to sustainably increase throughput to the downstream grinding circuit. UMS completed the detailed engineering, oversight of fabrication and construction and assistance with commissioning of the designed solution. 2020
South Africa Sepflour Nokeng Detail review of the scoping study proposal. 2020
Senegal Afrigold Gold Bankable feasibility study. 2018
South Africa Sasol – Brandspruit Colliery Impumelelo shaft Coal Design of the shaft complex. 2013-2014
South Africa Sasol – Shandoni shaft Coal Detailed engineering design for permanent infrastructure for the man and material shaft including a 65-tonne man cage. 2013-2014
South Africa
Impala 17 shaft Platinum Sinking designs for the main, ventilation and refrigeration shafts. 2008
ENGINEERING, DESIGN & CONSULTING PROJECTS
SINKING PROJECTS
(VERTICAL & DECLINE)
DEVELOPMENT AND MINING
PROJECTS
UNDERGROUND CONSTRUTCTION AND REFURBISHMENT PROJECTS
PROCESS PLANT
PROJECTS

Engineering, Design & Consulting projects

Country Client Commodity Project scope Project status
South Africa South 32 – Mamatwan Mine Top-Cut Material Processing Manganese

The Pre-Feasibility Study (PFS) aimed at identifying the most practical and effective processing solution for the top-cut material.

The PFS was required to investigate, select, and consolidate the preferred processing alternative to progress into Feasibility Study (FS), develop a Total Installed Cost (TIC) estimate and schedule, and establish an FS scope to minimise the risk of cost overruns and/or schedule delays during the execution of the Project

February 2024
South Africa Ivanplats – Platreef Shaft 2 Platinum

UMS are fulfilling the role of the owners’ team for the Platreef Shaft 2 construction project. This includes supporting and managing the following contractors:

  • Murray and Roberts
    • Raise bore drilling
    • Diamond drilling
    • Shaft sinking – slipe, line and equipping
  • Stefanutti Stocks
    • Headgear slide/construction
    • Headgear structural construction
In Progress
South Africa Sibanye – Burnstone Plant Refurbishment Project Gold

Refurbishment and recommissioning of the Burnstone Gold Plant, which included the following:

  • Service, repair, refurbish and/or replace chosen mechanical, electrical and control & instrumentation equipment/spares at the Plant
  • Service, repair, refurbish and/or replace chosen civil and structural related infrastructure at the Plant
  •  Service, repair, refurbish and/or replace chosen mechanical, electrical and control & instrumentation equipment/spares at the Tailings Storage Facility (TSF)
  • Service, repair, refurbish and/or replace chosen civil and structural related infrastructure at the Tailings Storage Facility (TSF)
  • Commission the Process Plant and related facilities such that it is ready for production
February 2024
South Africa Pilanesberg Platinum Mines – Sedibelo Development Project Platinum

The design scope for UMS included:

  • Site layout and infrastructure
  • Chairlift decline and travelling ways.
  • Conveyor decline and “training decline”
  • Main decline
  • Level and access decline including workshop, ventilation pass and level dams.
  • Decline support (anchors, wetcrete and tendons)
  • Cover drilling
  • Raise boring
  • Brow stabilisation
September 2023
South Africa Impala 1# Platinum Full shaft audit of aging shaft infrastructure with upgrade/optimisation recommendations. 2021
South Africa Evander/Pan Africa Gold Design of a compensating tower thereby enabling safe pillar extraction of remaining ore reserves in an aging mine. 2019-2020
Botswana Karowe diamond mine Diamonds

The Karowe Underground Project (KUP) scope of works entailed the design and engineering for the blind sinking of two vertical shafts. The main production shaft will have a finished internal diameter of 8.5m and be sunk to a depth of 765m below surface level. The ventilation shaft will have a finished diameter of 6m and be sunk to a depth of 755m.

In addition to the shaft sinking activities, the scope of works includes the design and engineering for the equipping of the production shaft for permanent configuration and initial lateral development.

Brazil Ero Copper – Caraíba Pilar Mine Copper

The UMS scope included the design and construction of the new vertical mine shaft and underground rock handling arrangements The ERO Brasil Caraiba project.

Design scope was for a shaft  approximately 1,500m deep with a hoisting capacity of 2.2 million tonnes per annum of ore and waste from underground to surface. The shaft will also be capable of raising and lowering approximately 840 persons per day, to and from underground.

The underground rock handling system included haul truck tips for ore and waste rock, storage silos for run-of-mine and crushed ore and waste rock, an underground primary crushing station, and conveyors to transfer the rock to the vertical shaft.

To be completed in 2026
South Africa Sibanye Stillwater Ikamva Kloof mine Design of level declines. 2022
South Africa Vanadium Resources Vanadium Pre-feasibility and definitive feasibility study. 2021- 2022
South Africa New Denmark – Seriti Coal Design of new conveyors, man cages and platforms. 2020-  2021
Zimbabwe Zimplats Platinum Implementation of a debottlenecking project to sustainably increase throughput to the downstream grinding circuit. UMS completed the detailed engineering, oversight of fabrication and construction and assistance with commissioning of the designed solution. 2020
South Africa Sepflour Nokeng Detail review of the scoping study proposal. 2020
Senegal Afrigold Gold Bankable feasibility study. 2018
South Africa Sasol – Brandspruit Colliery Impumelelo shaft Coal Design of the shaft complex. 2013-2014
South Africa Sasol – Shandoni shaft Coal Detailed engineering design for permanent infrastructure for the man and material shaft including a 65-tonne man cage. 2013-2014
South Africa
Impala 17 shaft Platinum Sinking designs for the main, ventilation and refrigeration shafts. 2008
ENGINEERING, DESIGN & CONSULTING PROJECTS
SINKING PROJECTS
(VERTICAL & DECLINE)
DEVELOPMENT AND MINING
PROJECTS
UNDERGROUND CONSTRUTCTION AND REFURBISHMENT PROJECTS
PROCESS PLANT
PROJECTS

Sinking projects (Vertical & Decline)

Country Client Commodity Project scope Project status
Botswana Lucara (Karowe Mine) Diamonds Transition from open pit mining to underground via a production shaft (770 m) and ventilation shaft (728 m),including raise bored material handling ore passes, level development of 1550 meters in total, level construction, production shaft equipping and permanent winder supply and installation. Current –to be complete in 2025
Brazil ERO (Caraíba Pilar Deepening Project Brazil) Copper

The Pilar Deepening Project is designed to access deeper reserves of the Pilar Mine, which has been operating for nearly 40 years, first as open pit mine and thereafter as an underground mine with ramp access. The project includes a vertical shaft 6.3m in diameter and 1500m deep, with permanent facilities to hoist rock (ore and waste) and raise/lower personnel to this underground level. The shaft is being sunk in a unique raise-bore and slash method with follow-on shaft sidewall support and concrete lining. This method will improve the rate of advance in shaft sinking, delivering the commissioned shaft in quicker time. The project is being executed by UMS through four packages of work; (i) design, engineering and procurement services for the new shaft, (ii) shaft pre-sink construction and change over, (iii) main sink construction, (iv) shaft equipping and commissioning. 

USA

WiPP – (Waste Internment Pilot Project LLC)

Hazardous waste

Sink a shaft (693 m X 7.92 m diameter) plus lateral development of 1750 m.

2019 – 2024
South Africa Pilanesberg Platinum Mines (PPM)
East block access project
Platinum Development of 3 declines to transition from open pit mining to underground. Project started 2022
India Vedanta / Hindustan Zinc Limited (HZL)  – Rampura Acgucha Mine Three shaft project Zinc Sinking of 3 concrete lined shafts and equipping of the main shaft including station construction.  Development of twin decline.
Main shaft: 950 m X 7.5 m diameter.
North vent shaft: 497 m X 7.5 m diameter.
South vent shaft: 507 m X 7.5 m diameter.
Trackless development.
2010 – 2019
Democratic Republic of the Congo Kibali Gold (Barrick) – Kibali Mine Single Shaft project Gold Main Shaft 760 m x 7.0 m diameter.
Three phase scope of works: 1. Shaft sinking and early development 2. Shaft equipping, winder installation, rope up and commissioning 3. Shaft manning, underground construction, including electrical and mechanical installations.
2012 -2018
South Africa Bafokeng Rasimone Platinum Mine (Joint Venture) – Styldrift Merensky Phase 1 sinking and equipping Platinum Sinking of Main (760 m X 10.5 m diameter) and Services Shaft (730 m X 6.5 m diameter); lateral infrastructure development and associated underground construction works; equipping of Service Shaft and station; trackless development. 2015 -2017
India Teesta III – Pressure shafts Hydro Two pressure shafts of 750 m X 5.4 m diameter each. 2012
South Africa Afplats (Pty) Ltd, Leeuwkop Mine Complex Platinum Sinking of the Main Shaft ( 1000 m X 10.2m diameter). 2007 – 2012
South Africa Lonmin PLC – Karee 3 Shaft – Underground 2 sub-incline & trackless development Platinum Sinking of decline shaft (649 m) with further horizontal development, including infrastructure for declines – silos, settlers, conveyors, bulkheads On-reef development (± 165 000m³)  and ore handling. 2013 – 2019
South Africa Hernic – Bokfontein Mine – Development of a twin decline system and stoping Twin decline system  (3.5 m X 6.0m diameter) and 120ktm stoping. 2011 – 2013
South Africa Impala 17 Three Shaft Project Platinum Sinking of 3 shafts;  Main (1932.8m X 10.0 m diameter); Vent (1764.2m X9.5 m diameter); and Fridge Shafts (1432m X 6.0 m diameter with the associated lateral development between the shafts.  Installation of the ore-pass systems and civil works.
Concrete lining with cast in items for permanent equipping.
Trackless development.
2010 – 2014
South Africa Bafokeng Rasimone Platinum Mine – Styldrift Shaft sinking JV Platinum Sinking and equipping of a Main and Services Shafts, including shaft and station equipping, lateral infrastructure development and associated underground construction works (bulkheads and conveyor belts installation). Trackless development.
Main Shaft: 760m X 10.5m diameter.
Service Shaft: 730m X 6.5m diameter.
2015 – 2017
South Africa Impala 16 Twin Shaft Project Platinum Sinking of the Main shaft (1665 m X 10.0 m diameter) and Vent shaft (1390 m X 6.8 m diameter); lateral development between the shafts; installation of the ore-pass systems and civil works; installation of the station infrastructure including pumps, settling system and conveyor belts; permanent equipping and commissioning of the Main Shaft system. 2006 -2014
Mali Somilo S.A, Yalea Underground Mine – Mali Gold Single decline system (876 m) plus development and ancillary reef and waste development (380 000 m³ / 4.5m H x 4.5m W).
Long hole Caving Mining.
2006 – 2010
South Africa Phakisa Phase 3 Gold Sinking of a main shaft (2471m X 7.1m diameter) including equipping of shaft infrastructure. 2006 – 2008
Switzerland Gotthard Tunnel Sedrun Shaft – (Joint Venture) Transport Sinking of a ventilation shaft of 850 m X 8.5 m diameter and TMM development 2002
South Africa Impala 14A Vent – Sinking of Ventilation Shaft Platinum 1080 m X 5.1 m diameter. 2002
South Africa Vaal Reefs No. 11 Main Shaft Gold 2.460 . X 10.75 m diameter. 2000
Brazil Morro Velho – Raposos No. 5 Sub Shaft Sinking of a sub-shaft (678 m X 6.5m diameter). 1992
Laos Houay Ho Hydropower station – headrace shaft Hydro Sinking of a 714 m X 4.0 m diameter shaft. 1996
Indonesia Pt. Aneka Tambang Mine service shaft Sinking of a 320m X 6.2 m diameter shaft. 1997
Chile El Bronce – Decline development Decline system (2300 m / 2.5m H x 2.7m W). 1995
ENGINEERING, DESIGN & CONSULTING PROJECTS
SINKING PROJECTS
(VERTICAL & DECLINE)
DEVELOPMENT AND MINING
PROJECTS
UNDERGROUND CONSTRUTCTION AND REFURBISHMENT PROJECTS
PROCESS PLANT
PROJECTS

Development and mining projects

Country Client Commodity Project scope Project status
South Africa Pilansberg Platinum Mines – Sedibelo Project Platinum

15km of Trackless Development.

2022-2023
South Africa Lonmin PLC Karee 3 shaft Platinum Trackless horizontal development and installation of various services (+/- 226,000m3). 2006 -2019
South Africa Hernic – Bokfontein mine Platinum 120 ktm of stoping plus trackless development. 2011 – 2013
South Africa Impala 16 twin shaft project Platinum On completion of the shaft sinking and equipping phase of our project we continued with trackless lateral development to the reef. 2006-2014
South Africa Anglo Platinum – Unki mine Platinum Bord and Pillar production mining of +/- 120 kilotons per month. 2008
South Africa Everest Aquarius mine Platinum Trackless mining of +/- 250,000 kilotons per month including triple decline system with end sizes 4 m (H) X 4.5 m(W). 2006 – 2008
South Africa Everest Aquarius mine Platinum Conventional mining of +/- 40,000 kilotons per month. 2007 – 2008
South Africa IMR Buffelsfontein Chrome Mine Lesedi shaft Chrome Trackless mining of 70,000 kilotons per month including decline development, stoping and construction. 2007-2008
ENGINEERING, DESIGN & CONSULTING PROJECTS
SINKING PROJECTS
(VERTICAL & DECLINE)
DEVELOPMENT AND MINING
PROJECTS
UNDERGROUND CONSTRUTCTION AND REFURBISHMENT PROJECTS
PROCESS PLANT
PROJECTS

Underground construction and refurbishment projects

Country Client Commodity Project scope Project status
South Africa Harmony Kusasalethu shaft refurbishment project Gold Re-equipping of sub vent shaft. 2022-2023
South Africa Impala 20 Shaft refurbishment project Platinum Refurbishment of loading bin, settler, shaft barrel, silos, and headgear bin.
Grouting of the dam wall.
2022-2023
South Africa Harmony Target Mine shaft refurbishment Gold Removal of old brattice wall. 2021- 2022
South Africa RBM Styldrift mine bulkhead installations Platinum Underground mining construction and replacement of bulkheads. 2019- 2021
South Africa South 32 Wessels mine – shaft rehabilitation Manganese Extensive shaft rehabilitation and repair work. Started 2019 and ongoing
South Africa Pan Africa Evander shaft refurbishment Gold Design and installation of a compensating tower in an old shaft at Pan Africa’s Evander Mine, enabling the mine to undertake safe pillar extraction to extract remaining ore reserves. 2019-2020
South Africa Orion Minerals Copperton mine Copper Dewatering and initial refurbishment of the mine after care and maintenance. 2017- 2019
South Africa Evander 7 shaft Gold Shaft repair and steelwork replacement to extend life of mine. 2017-2018
South Africa Anglo Platinum – Turffontein Mine Platinum Shaft rehabilitation and shaft steelwork replacement. 2008
South Africa Moab Khutsong Gold Excavation of underground silos and ore passes. 2007- 2008
South Africa Palabora Copper Excavation of #3 and #4 crusher chambers. 2002
Swaziland Maguga Dam Hydro Intake, diversion and outlet tunnels of 8m X 9m diameter and 485 meter in length. 1999
ENGINEERING, DESIGN & CONSULTING PROJECTS
SINKING PROJECTS
(VERTICAL & DECLINE)
DEVELOPMENT AND MINING
PROJECTS
UNDERGROUND CONSTRUTCTION AND REFURBISHMENT PROJECTS
PROCESS PLANT
PROJECTS

Process plant projects

Country Client Commodity Project scope Project status
South Africa Burnstone – metallurgical plant Gold ore
  • The Burnstone Metallurgical Plant with a capacity 125kT/m milled ore, has been mothballed since 2012
  • The UMS scope was to assess the condition of key and critical equipment is all engineering disciplines including Mechanical, Electrical, control and instrumentation, civil/ structural and piping
  • This assessment included refurbishment or replacement cost sourcing and capital budge estimate development based on our inspections and assessments
  • The CBE was used to form the budget for the refurbishment works
  • UMS engaged with site works to perform the necessary physical construction/ refurbishment activities and facilitated the works of all OEMs/ Vendors
  • UMS facilitated the procurement activities on behalf of the client and assessed each order technically, worked with the client’s procurement team and delivered the procured items to site for installation and commissioning
  • The scope included up to C2 commissioning on all equipment

2022-2023

Zimbabwe Zimplats – Zimplats Selous Metallurgical Complex (SMC) Platinum
  • SMC had completed a feasibility study on the implementation of a secondary crusher circuit to crush the -135; +50 mm size fraction prior to the milling Circuit – Called Feed Preparation
  • UMS completed the debottlenecking project which sustainably increased throughput to the downstream grinding circuit. UMS completed the detailed engineering, oversight of fabrication and construction and assistance with commissioning of the designed solution
  • The client has implemented this solution and has found that it there are many more opportunities to de bottleneck within the Zimplats group, with the additional throughput now made available
2019-2020
Zimbabwe Zimplats HPGR project Platinum

Design and install a solution to increase the current SMC pebble crushing capacity and efficiency by means of increasing cone crusher feed bin capacity; including installation of standby cone crusher unit as well as the installation of a High Pressure Grinding Roll (HPGR) unit.

These modifications increased the pebble crushing circuit throughput to 120t/hr.

2019
Mozambique Manica – Mutupa Mining and Processing (MMP) Gold
  • Mets Projects SA, a subsidiary of UMS Group, was contracted by Mutupa Mining and Processing (MMP) to complete a Feasibility Study and execution work for the Manica Gold Plant in Mozambique. The Manica gold plant treats 42 000 t/month of ROM ore from the Manica resource
  • UMS successfully completed the detailed design, procurement, site construction assistance and commissioning assistance
2020 – January 2023 when plant was commissioned
Brazil Ero Copper Corp – Tucumã Project Copper
  • UMS was employed as the owners’ team for the basic engineering phase of the project that was completed in February 2023
  • The UMS scope of work included oversight for project management, engineering, procurement and project controls
  • The project scope included the surface infrastructure, the crushing and screening plant and the copper processing plant. Also included in our scope was the hydrology studies and tailings design

2022 – 2023

Plant owner is currently undertaking construction directly

South Africa Kumba – Kolomela crushing operation Iron ore
  • Design, construct, commission and operate a crushing plant consisting of a three-stage crushing circuit with the relevant screening operations to produce 132 000 tonnes per month
  • Screened material to be stockpiled in 2 separate stockpiles with a capacity of 30 000 tonnes of each
  • The primary and secondary crushers were operated in open circuit and the tertiary crusher was configured to operate in a closed-circuit configuration with the primary screen
2016 -2019
South Africa Sibanye Stillwater – Kloof Operations SRD Crushing Plant Gold

We were requested to install and operate and transfer a mobile crushing and screening plant for the client.

The Crushing and Screening Plant required to be designed based on the following key parameters:

  • Total feed rate of 150 000 to 180 000 tons per month toll treatment contract
  • Crusher design feed rate of 455 t/h
  • Two screened products are to be produced namely Pebbles (-150mm +75mm) and Fines (-20mm)

The plant was sold in 2019.

2018 -2019